The Utility Selector task evaluates the child tasks using Utility Theory AI. The Utility Selector is based on the implementation suggested by the Game AI Pro book. The task with the highest utility value will be selected. An existing running branch can be aborted when its evaluator has Block During Execution disabled. The Utility Selector task reevaluates its children every tick.

The Utility Selector runs the branch with the highest evaluator value.

The Utility Variable Evaluate returns a utility value based on a constant float value. In the example above the leftmost branch has a utility value of 1, middle has a value of 3, and rightmost has a utility value of 2. The middle branch is selected because it has the highest utility value.

The highest-utility branch succeeds and the Utility Selector finishes with Success.

This is the same tree as the first image. The Wait task completed and return a status of success. The Utility Selector acts similar to the Selector task in that it will return success as soon as the first child returns success. Because the middle branch returned success the Utility Selector returned a success.

The highest-utility branch has failed and the next-highest branch is running.

This example is similar to the first tree, except instead of the middle branch returning success it returns failure. The middle branch executed first because of the utility value of 3, but because it returned failure the Utility Selector moved onto the next highest branch which is the rightmost branch.

The next-highest utility branch succeeds after the preferred branch failed.

Continuing from the last image, the rightmost branch returns success after 1 second and because of that success the Utility Selector then returns success.

All utility branches and the Utility Selector have finished with Failure.

Similar to the Selector task, if all of the children return failure then the Utility Selector will also return failure.

The second branch runs because its current utility value is highest.

The Utility Selector is a responsive task. In this screenshot the second branch is selected because it has the highest utility value of 3.

The third branch takes over after its changing utility value becomes highest.

Every tick the utility value of all of the branches update. The Utility Curve Evaluator will evaluate a curve based on the time elapsed. With each tick the utility value will update and after 10 seconds the third branch has a higher utility value than the second branch. The third branch aborts the second branch even though it hasn’t completed because it has a higher utility value. These examples have Block During Execution disabled on the evaluators. The option is enabled by default and gives a running child an infinite utility value, keeping its branch selected until completion. Disable it to allow the changing scores to preempt a running branch.

The first branch takes over after its changing utility value becomes highest.

The utility value doesn’t stop updating until the Utility Selector ends. The first branch aborts the third branch because its utility value eventually gets to be higher than the third branch.

Utility Value

Behavior Designer includes two Utility Evaluators:

  • Utility Variable Evaluator: Returns a utility value based on a float SharedVariable.
  • Utility Curve Evaluator: Returns a utility value based on a curve.

If you want to return a different utility value based on another evaluator you can inherit the Utility Evaluator abstract class. The only method that you need to implement is the GetUtilityValue method:

using Opsive.BehaviorDesigner.Runtime.Tasks.Decorators;

public class MyUtilityEvaluator : UtilityEvaluator
{
   /// <summary>
   /// Returns the utility of the decorator. The higher the utility the more likely the task will run next.
   /// </summary>
   /// <returns>The utility of the decorator.</returns>
   public override float GetUtilityValue() { return 5; }
}

The sample class overrides the GetUtilityValue and returns a constant 5 value.